| 1. |
Prepare
sketches showing setting-out dimensions for each dry lining
box including height and hole size. |
| 2. |
Fix
each conduit pipe to noggins using suitable straps or cable
ties. Fixings at 1m centres are adequate for vertical conduit
pipe. Horizontal runs and bends more than 45° should be
avoided. |
| 3.
|
To
allow future installation of dry lining boxes, each conduit
pipe end should be left approximately 100mm longer than box
position and should not be fixed closer than 600mm to the box.
|
| 4. |
Install
the main 'first-fix' pipework leaving joints below floor access
covers to allow connection to conduit pipework during 'second
fix' work. |
| 5. |
Using
setting-out dimensions on sketches, holes in plasterboard can
be cut to allow each conduit pipe to be pulled out through the
surface during plasterboard fixing work. |
| 6. |
During
'second fix' each dry lining box is installed by drilling a
26mm diameter hole for 15mm (nominal) conduit pipe. The conduit
can then be inserted through hole in box and should 'click'
into position leaving one or two conduit 'ribs' inside box.
|
| 7.
|
Slide
a length of 10mm Hep2O®
pipe through conduit pipe from the floor access above. Pull
out enough Hep2O®
from dry lining box to allow a sufficient hand grip for jointing.
Connect a demountable elbow to pipe then slide whole assembly
through plasterboard hole and secure box into position. Conduit
pipe should ÔsnakeÕ within void to take up slack leaving
Hep2O®
protruding out of box. |
| 8. |
Pull
Hep2O®
pipe backwards from floor access panel until elbow is central
within dry lining box. Cut pipe to length and connect to Hep2O
joint left during 'first-fix'. |